Approximate schedule for the construction of an all weather arena

20 metre X 40 metre

Ground Works

Strip off topsoil from the site and stockpile.

Dig down to correct levels.

Excavation of drainage.

Digging of outlet to ditch or soak away.

Laying of wavy coil pipe.

Filling of Trenches with 40mm clean stone.

Fencing

Concreting of fencing post in position, post to be 150mm x 75mm.

Fitting of timber rails.

Fitting of 150mm x 75mm kickboards.

Fitting of timber gate, (gate to size your choice) all ironwork will be galvanised and timber will be treated.

Laying of sub-base

Membrane fitted.

Area filled with clean stone.

Stone rolled into place.

 Membrane then fitted into place.

Arena surface

Surface of your choice to be laid.

Any extra work you required would be carried out then e.g. lighting, access roads.

Arena completed

The site to be left neat and tidy,

ready for you to enjoy!


Prices for other sizes and layouts are available on request. We would hope to complete a 20m x 40m arena in 7 to 10 days depending on the weather.